Skip to content
Design-Bid-Build – FBH – Image

Project Delivery Methods

Design-Bid-Build (DBB)

Design-bid-build (DBB) is a traditional construction project delivery method that involves the completion of three distinct phases in sequence. Construction does not begin until the design process is complete (and a bid accepted), so there is no overlap between design and construction.

The Design-Bid-Build Process in Construction

As the name implies, DBB comprises three distinct phases.

Design
collapse icon

In this phase, the owner or the agency contracts a design engineer or architect to develop a comprehensive set of construction drawings that forms the basis of the subsequent bidding process. The architect or design engineer first works closely with the owner to understand vision and translate that into a document. Design includes translation of these needs into a comprehensive set of engineering drawings that contractors can use to build the desired structure. An architect will sometimes work with other professionals such as plumbing and electrical engineers on specific sections of the design documents. A thorough reiteration of the documents then readies it for public bidding.

Bid (or tender)
collapse icon

General contractors bid on the design documents after consulting with subcontractors for various aspects of the construction process, including HVAC installation, landscaping, insulation, and more. The final bid typically outlines the cost of materials and labor. The scope for work might be refined during the bidding process. During this stage, the roles of the various entities involved are also well laid out. Once all bids come in by the specified date, the owner may decide to scrap or modify the project or proceed with a specific general contractor.

Build
collapse icon

The general contractor begins and completes the construction of the project while supervising and getting work done from a series of subcontractors. Work often executes in a specific sequence. The general contractor signs on to a specific scope of work and design cannot be altered at this late stage.

Design-Bid-Build vs. Design-Build

As opposed to DBB, design-build is a newer project delivery method that does not include clear compartments between the owner and the builder. Contractors come in much earlier during the process and collaborate with the design team.

The traditional design-bid-build project delivery method process is advantageous because it has:

A Clear Distinction Between Teams

The architect or designer and the contractor each stay in their own lanes, which makes it easier to hold professionals accountable for missed deadlines or ballooning expenditures.

Greater Transparency

Because roles are more clear cut in the DBB method, the project owner enjoys greater transparency into the process and might therefore be able to spot potential problems faster.

More Opportunities for Fair Bidding

The bidding process is usually open to a wide set of professionals and the public bidding window ensures competitive quotes, which is especially beneficial for large-scale public works projects.

Encourages Professionals to Play to their Strengths

DBB plays to designers’ and contractors’ strengths. In this project delivery method, they can concentrate and build upon their niche, instead of trying to be all things to all people.

Greater Responsibility on Owner

The owner in the DBB process creates two separate contracts for the designer and the builder. This can be an advantage where the owners need a greater say in project execution. However, there is a downside too: Any snags in the execution ripple up to the owner.

The DBB process has its fair share of challenges. They include:

Possibility of Longer Timelines

Because the sequential DBB method waits for each party to completely finish its tasks before moving on to the next one, the project might have a greater chance of being delayed.

Challenging Construction Implementations

Not all designs are easily constructed. Keeping construction professionals divorced from the design process might encourage creativity but sometimes challenging designs can’t be easily translated into finished projects. A lack of input from all stakeholders early on in the process can highlight problems much further down the road and lead to more time crunches and expensive redesigns and rebids.

Owner Bears Brunt of Project Challenges

Change orders, busted timelines all fall on the owner’s shoulders as they develop two separate contracts–one with the designer and the other with the contractor. Since the owner supervises both parties, they are also responsible for the problems associated with each.

The design-build project delivery method enjoys a few advantages as well. They include:

Shorter Timeline

Because the design-build process allows contractors to begin work on the project before the designs have been firmly established, the method enables faster turnarounds.

Fewer Change Orders

The DB process leads to greater collaboration between the stakeholders and, equally important, this collaboration takes place early in the project. As a result, all teams are able to put out any potential fires early. This leads to fewer problems down the road and fewer troublesome change orders and rework. Because of these efficiencies, design-build advocates also maintain that the process is less expensive than the DBB approach.

While design-build is growing in popularity, it is not without its own set of challenges. These include:

No ownership of problems

Because there is significant overlap between various stakeholders, it becomes easier for them to pass the buck to the other party when problems do occur. It is more difficult to track mistakes and find the entity responsible for the fix.

No competitive bidding

The design-build method leans on the design-builder to execute the project, which means the owner might not always get the most competitive price as the bidding process gets sidelined.

Design-bid-build or Design-build

Which method is right for your project?

Since each approach to construction project delivery has both advantages and disadvantages, it might be difficult to know which one to run with.

Design-bid-build or Design-build

Examples of Design-Bid-Build Projects

As the following examples illustrate, DBB projects can take a variety of forms–from buildings to arenas and infrastructure projects.

Cloud-Based Construction Projects

No matter which project delivery approach you choose, cloud-based construction management software involves all relevant stakeholders at the right stage and keeps everyone in the loop at all times.

Accessing updated information from the cloud ensures all parties are working with the same data. This aids effective communication, faster approvals, and speedier completion of projects. Trimble’s ProjectSight project management solution, along with the Trimble Connect collaboration platform empowers construction professionals to collaborate and manage their project easily and with the best outcomes.

Processing...
Please Wait.
We are migrating your Account information.
Attention
We tried to combine the products in your guest cart with your saved cart, but we encountered an issue while merging them. When choosing a subscription, please select either monthly or yearly as they cannot be combined. Kindly review your cart before proceeding to checkout.
Cart Updated
undefined

undefined:
undefined
Attention
Cart Updated
The items in your cart have been updated for two reasons. Firstly, the prices now match the currency linked to your account address. Secondly, some items have been removed because they are not available for purchase in your region. Please review your cart before proceeding.

undefined:
undefined
Cart Updated
The items in your cart have been updated for two reasons. Firstly, you've added too many of one item to your cart. Secondly, some items have been removed because they are not available for purchase in your region. Please review your cart before proceeding.

undefined:
undefined
Cart Updated
The items in your cart have been updated for three reasons. Firstly, the prices now match the currency linked to your account address. Secondly, you've added too many of one item to your cart. Thirdly, some items have been removed because they are not available for purchase in your region. Please review your cart before proceeding

undefined:
undefined
Cart Updated
Your currency has been changed to match the currency associated with your account address.
Cart Updated
Your cart has been updated for two reasons. First, the prices now reflect the currency associated with your account address. Second, you've added too many of one item to your cart. Please review your cart before proceeding.
Cart Updated
While combining the products in your guest cart with your saved cart, at least one item in your cart has exceeded the maximum allowable quantity. Please review and correct your cart before proceeding to checkout.